Federal Enforcement Data

CITY OF GLENDALE, GLENDALE WATER & POWER

(Operator ID:31986 - CURRENTLY ACTIVE OPID)

The reports below provide federal enforcement data since 2006. This information includes both a summary of and specific details pertaining to enforcement cases against this operator. Enforcement by PHMSA's partner State agencies are not included in these reports. Non-Enforcement Data for CITY OF GLENDALE, GLENDALE WATER & POWER.

Enforcement Actions

For more information on each enforcement type see the Enforcement Type Glossary

CITY OF GLENDALE, GLENDALE WATER & POWER Federal Enforcement Cases
All Pipeline Systems (1): 2006-2023
2023 YTD 2022 2021 2020 2019 2018 2017 2016 2015 2014 2013 2012 2011 2010 2009 2008 2007 2006 Total
Cases Initiated 0 0 0 1 0 0 0 0 1 0 0 0 2 0 1 0 0 0 5
Cases Resolved 0 1 1 0 0 0 0 0 1 0 0 0 3 0 0 0 0 0 5
Penalties Proposed 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Corrective Action Orders Issued 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Cases Initiated: These are the yearly total of civil administrative enforcement actions that PHMSA has brought against pipeline owners and operators. It does not reflect those cases which the agency has referred to other Federal officials for criminal prosecution, nor does it include more egregious civil cases that are referred to the U.S. Department of Justice for judicial enforcement. The table shows the total number of Corrective Action Orders, Notices of Probable Violations, Notices of Amendment, Warning Letters, and Notices of Proposed Safety Orders issued in a given year.

Cases Resolved: These are the yearly total of PHMSA actions taken to resolve the various types of enforcement actions against operators. This includes the number of Corrective Action Orders, Final Orders, Notices of Amendment, and Consent Orders that have either been closed or issued in a given year. When an enforcement action is shown as "closed", PHMSA has verified that all of the corrective actions have been successfully completed and that any inadequate procedures that were identified successfully addressed. Enforcement actions shown as "issued" mean that corrective actions have been established that are acceptable to PHMSA, and that civil penalty assessments have been finalized.

For more information on each enforcement type see the Enforcement Type Glossary.

CITY OF GLENDALE, GLENDALE WATER & POWER Federal Enforcement Cases
All Pipeline Systems(1): 2006-2023
Case Number Date Opened Date Closed Type Subject PHMSA Region Status Proposed Penalty Assessed Penalty Collected Penalty Final Compliance Order
52021037NOPV 09/17/21 04/12/22 Proposed Compliance Order (consent order)
Warning Item
Operations - Gas Pipelines
Procedure Manuals - Gas Pipelines
Public Awareness - Gas Pipelines
Qualification of Pipeline Personnel - Gas Pipelines
WESTERN CLOSED $0 Yes
520160018W 10/06/16 10/06/16 Warning Letter Emergency Response - Gas Pipelines
WESTERN CLOSED $0 No
520120010M 04/10/12 07/05/12 Notice of Amendment Emergency Response - Gas Pipelines
Material Joining other than Welding - Gas Pipelines
WESTERN CLOSED $0 No
520120009W 04/09/12 04/09/12 Warning Letter Maintenance - Gas Pipelines
WESTERN CLOSED $0 No
520100009 03/02/10 02/15/12 Proposed Compliance Order Drug and Alcohol Testing - General
General - Gas Pipelines
WESTERN CLOSED $0 Yes
Totals        $0 $0 $0  

Sources

  1. PHMSA Safety Monitoring and Reporting Tool (SMART)and the Work Management System as of May 2, 2023.

For comments and questions on the information presented on this site, please send us feedback.

Feedback | FOIA | Information Highlights | Privacy Policy | Accessibility Policy | ©2005-2023 PHMSA | DOT Home | PHMSA Home | PSA Forum | Adobe Reader | Generated: 05/03/23 12:32:55 AM