Overview
Project No. | 1005 |
---|---|
Contract No. | 693JK32310002POTA |
Research Award Recipient | Blue Engineering and Consulting Company 6011 University Blvd, Suite 220 Ellicott City, MD 21043 |
AOR/TTI | Yasmin Alamin Katherine Roth Andrea Ceartin Kevin Ritz |
Researcher Contact Info | Filippo Gavelli, Ph.D., P.E.; fgavelli@blueeandc.com; 410-680-3568 |
Project Status | Active |
---|---|
Start Fiscal Year | 2023 (09/30/2023) |
End Fiscal Year | 2025 (09/30/2025) |
PHMSA $$ Budgeted | $806,522.00 |
Main Objective
The objective of this project is to develop experimental data to validate the appropriateness and effectiveness of passive fire mitigation systems subject to fire impingement. Additionally, the project will develop criteria for hazard modeling of these passive fire mitigation systems, and define criteria for the onset of structural failure of structural steel or pressure vessels exposed to fire. The project deliverables will support PHMSA in its ongoing efforts to improve LNG fire safety.
Public Abstract
The project team will build upon recently completed, directly relevant work for PHMSA and others, and its deep knowledge and expertise of LNG facilities, hazard modeling tools, and NFPA 59A standards development, to achieve the goals set forth in the project statement. The project team will leverage publicly available data on passive fire mitigation (PFM) systems as well as direct collaboration with PFM manufacturers and plant designers; the team will also collaborate closely with PHMSA and a knowledgeable Technical Advisory Panel (TAP). Physical testing will benefit from the pool fire setups available at the world-renowned Texas A&M Engineering Extension Service (TEEX) fire training facility, which also provides a wealth of experience and a long track record of safety.
Relevant Files & Links
Quarterly/Annual Status Reports
1st Quarterly Status Report - Public Page
693JK32310002POTA - 1st Quarterly Report - PUBLIC 191222.pdf
2nd Quarterly Status Report - Public Page
693JK32310002POTA - 2nd Quarterly Report - PUBLIC 240329.pdf
3rd Quarterly Status Report - Public Page
693JK32310002POTA - 3rd Quarterly Report - PUBLIC 240628.pdf
4th Quarterly Status Report - Public Page
693JK32310002POTA - 4th Quarterly Report - PUBLIC 240930.pdf
5th Quarterly Status Report - Public Page
693JK32310002POTA - 5th Quarterly Report - PUBLIC 241230.pdf
6th Quarterly Status Report - Public Page
693JK32310002POTA - 6th Quarterly Report - PUBLIC 250331.pdf