Operator:PECO Energy Company
Type:Program
Title:Removal of line reclassified as non-transmission (20% SMYS)
Synopsis:

Review of operational records identified that a line with MAOP of 250 psig (20.1% SMYS) had never operated above 235 psig (18.9% SMYS). MAOP was reduced. Valve changes were made at the pressure reducing station. The line was removed from the IM program.

Status: Acknowledged, States: PA
Response Basis:

PHMSA has received your notification of a change to your IM program. This information will be incorporated into PHMSA inspection planning.