 » Assessment
   » Assessment Methods
     » Other Technology

Related Rule Sections:

Related Protocol Questions:

B.01 Assessment Methods

Verify that the operator's Baseline Assessment Plan (BAP) specifies an assessment method(s) for each covered segment that is best suited for identifying anomalies associated with specific threats identified for the segment. [§192.919(b), §192.921(a), §192.921(c), and §192.921(h)]

D.10 Wet Gas ICDA Programmatic Requirements

If the operator elects to use ICDA to assess a covered segment operating with electrolyte present in the gas stream (wet gas), verify that the operator develops and implements an ICDA plan in accordance with §192.927 which addresses the following. [§192.927(b)]

F.02 Reassessment Methods

Verify that the approach for establishing the reassessment method is consistent with the requirements in §192.937(c). [§192.937(c) and §192.941]