PHMSA Gas Transmission (GT) Integrity Management
Time: 06/19/2013 03:54 AM

Rule Section: §192.933(c)

Schedule for evaluation and remediation.

Rule Hierarchy:

Rule Language:

An operator must complete remediation of a condition according to a schedule that prioritizes the conditions for evaluation and remediation. Unless a special requirement for remediating certain conditions applies, as provided in paragraph (d) of this section, an operator must follow the schedule in ASME/ANSI B31.8S (ibr, see §192.7), section 7, Figure 4. If an operator cannot meet the schedule for any condition, the operator must justify the reasons why it cannot meet the schedule and that the changed schedule will not jeopardize public safety. An operator must notify OPS in accordance with §192.949 if it cannot meet the schedule and cannot provide safety through a temporary reduction in operating pressure or other action. An operator must also notify a State or local pipeline safety authority when either a covered segment is located in a State where OPS has an interstate agent agreement, or an intrastate covered segment is regulated by that State.

Related Topics:

Related Protocol Questions:

PHMSA Home | Pipeline Safety Website | Feedback | Privacy Policy | FOIA