PHMSA Gas Transmission (GT) Integrity Management
Time: 08/27/2014 11:07 AM

Rule Section: §192.927(c)(1)

Preassessment.

Rule Hierarchy:

Rule Language:

In the preassessment stage, an operator must gather and integrate data and information needed to evaluate the feasibility of ICDA for the covered segment, and to support use of a model to identify the locations along the pipe segment where electrolyte may accumulate, to identify ICDA regions, and to identify areas within the covered segment where liquids may potentially be entrained. This data and information includes, but is not limited to -

(i) All data elements listed in Appendix A2 of ASME/ANSI B31.8S;

(ii) Model data.

Information needed to support use of a model that an operator must use to identify areas along the pipeline where internal corrosion is most likely to occur. (See paragraph (a) of this section.) This information, includes, but is not limited to, location of all gas input and withdrawal points on the line; location of all low points on covered segments such as sags, drips, inclines, valves, manifolds, dead-legs, and traps; the elevation profile of the pipeline in sufficient detail that angles of inclination can be calculated for all pipe segments; and the diameter of the pipeline, and the range of expected gas velocities in the pipeline;

(iii) Operating experience data.

Operating experience data that would indicate historic upsets in gas conditions, locations where these upsets have occurred, and potential damage resulting from these upset conditions; and

(iv) Other data.

Information on covered segments where cleaning pigs may not have been used or where cleaning pigs may deposit electrolytes.