Rule Section: §192.921(g)

Newly-installed pipe.

Rule Hierarchy:

Rule Language:

An operator must complete the baseline assessment of a newly- installed segment of pipe covered by this subpart within ten (10) years from the date the pipe is installed. An operator may conduct a pressure test in accordance with paragraph (a)(2) of this section, to satisfy the requirement for a baseline assessment.