D.06 Dry Gas ICDA Programmatic Requirements

If the operator elects to use ICDA, verify that the operator develops and implements an ICDA plan in accordance with 192.927.

  1. Verify that the operator developed a documented ICDA plan [192.927(c)]

  1. Verify that the operator's plan contains provisions for carrying out ICDA on the entire pipeline in which covered segments are present, except that application of the remediation criteria of 192.933 may be limited to covered segments. [192.927(c)(5)(iii)]

  1. Verify that the operator implements the ICDA plan. [192.927(c)]