Question: Can operators count prior assessments of low-risk segments used as baselines against the requirement to complete 50% of their covered mileage by December 17, 2007?

Answer: Yes. The rule requires that operators prioritize covered pipeline segments for baseline assessment based on risk. Thus, the schedule in the Baseline Assessment Plan generally should show that the highest risk segments are scheduled for assessment prior to the lower risk segments. However, this does not preclude an operator from using a prior assessment for a baseline, even if the segment(s) covered by that assessment later turn out to be relatively lower risk.

These Frequently Asked Questions (FAQs) are intended to clarify, explain, and promote better understanding of the pipeline integrity management rules. These FAQs are not substantive rules and do not create rights, assign duties, or impose new obligations not outlined in the existing integrity management regulations and standards. Requests for informal interpretations regarding the applicability of one or more of the pipeline integrity management rules to a specific situation may be submitted to PHMSA in accordance with 49 C.F.R. § 190.11.
PHMSA Home | Pipeline Safety Website | Feedback | Privacy Policy | FOIA