FAQ-213: Prioritizing excavations for ECDA

Go To FAQ#:

Question: At what point during ECDA does one move from severe, moderate, minor to immediate, scheduled, monitored?

Answer: The categories of "severe", "moderate", or "minor" refer to the severity of indications (see Section 4.3 of NACE RP0502-2002). Each operator is responsible for determining these severities during the indirect inspection step.

"Immediate", "scheduled", or "monitored" refer to the priority for excavation (see Section 5.2 of NACE RP0502-2002). After each indication has been categorized according to its severity, the operator is responsible for determining the urgency (prioritization) of excavation of indications for direct examination (see 192.925(b)(2)(iii)).

Identified defects then must be scheduled for remediation (see 192.933(c)), or classified as "immediate", "one-year", and "monitored" repair conditions (see 192.933(d)). This classification must be done once the operator has sufficient information to "discover" remediable defects.

These Frequently Asked Questions (FAQs) are intended to clarify, explain, and promote better understanding of the pipeline integrity management rules. These FAQs are not substantive rules and do not create rights, assign duties, or impose new obligations not outlined in the existing integrity management regulations and standards. Requests for informal interpretations regarding the applicability of one or more of the pipeline integrity management rules to a specific situation may be submitted to PHMSA in accordance with 49 C.F.R. § 190.11.