FAQ-200: PIC for lines with multiple possible MAOP

Go To FAQ#:

Question: Our company constructed a line many years ago with an MAOP of 1000 psi. Recently we extended the line and, expecting market growth, put in pipe with an MAOP of 1201 psi. But the only supply to the new segment is the old line. Can we look for HCAs in both segments using MAOP=1000 psi? If we do so, are we obligated to go through a derate/uprate procedure?

Answer: Under the circumstances described, the MAOP of the line is 1000 psi, governed by the capability of the most limiting component (the old line). Potential impact circles can be calculated using the 1000 psi MAOP. Use of the line at higher pressure would require that the line be uprated, in accordance with Part 192 requirements. The management of change element of the operator's integrity management program should require that HCAs be re-evaluated, using the new MAOP, prior to any such uprate.

These Frequently Asked Questions (FAQs) are intended to clarify, explain, and promote better understanding of the pipeline integrity management rules. These FAQs are not substantive rules and do not create rights, assign duties, or impose new obligations not outlined in the existing integrity management regulations and standards. Requests for informal interpretations regarding the applicability of one or more of the pipeline integrity management rules to a specific situation may be submitted to PHMSA in accordance with 49 C.F.R. § 190.11.
PHMSA Home | Pipeline Safety Website | Feedback | Privacy Policy | FOIA